Workload traces are generated automatically by Moab during normal
execution. If you take a look in the "stats" directory you will see
"event" files. Here is what a valid entry looks like:
10:33:39 1160411619 job 754 JOBEND 1 1 wightman
wightman 600 Completed [batch:1] 1160411014 1160411014 1160411014
1160411619 - - - >= 0M >= 0M -
1160411014 1 0 -:- [RESTARTABLE] - - - 0
163.56 pbs 1 0M 0M 0M 0 2140000000
maka pbs - - [DEFAULT] - - 0.00 - - - - -
(all one 1 line)
- Douglas
On Mon, 2006-10-09 at 12:35 -0700, Corby wrote:
> I was trying to follow the format from
> http://www.clusterresources.com/products/mwm/docs/16.4.0simulations.shtml but realized quickly something was wrong. The problem is that I couldn't figure out what exactly. There are so many fields so there's a lot of variables when trying to figure out what part of it was wrong.
>
> I wasn't sure how the workload trace should work. In particular I
> wasn't sure if I needed to do jobcreate and then jobstart in order to
> make moab actually simulate the execution of a program.
>
> Because of the setup right now that I'm working with, I wasn't able to
> simply have Moab output some accounting records.
>
> -Corby Ziesman
>
>
>
> On 10/9/06, wightman <wightman at clusterresources.com> wrote:
> The workload trace entries are incorrect. Where did you
> obtain these
> records? Did Moab output them?
>
> - Douglas
>
> On Wed, 2006-10-04 at 14:52 -0700, Corby wrote:
> > I'm trying to run a simulation on moab, but every time I run
> moab it
> > just exits right away and the job I scheduled in my workload
> trace
> > doesn't seem to have run.
> >
> > I'm not quite sure how to set up the resource and workload
> traces, and
> > what fields are essential to getting a simulation to
> actually run at
> > all (I can then worry about making it reflect the hardware
> and
> > everything I want to simulate later, but first I just need
> it to
> > work).
> >
> > My workload trace just has these two entries:
> >
> > 00:00:20_01/01/00 946710020 job 1234 jobcreate 1 1
> root root
> > 86400 \
> > Completed [batch:1] 946710010 0 0 ethernet x86_64
> Linux >= 0
> > >= 0 \
> > - 0 1 -1 - - - /opt/moab/tracefiles/testprogram - -1
> 0
> > [DEFAULT] \
> > 1 0 0 0 0 0 - - - - - - - 0.0 - - - - - -
> > 00:00:30_01/01/00 946710030 job 1234 jobstart 1 1
> root root
> > 86400 \
> > Completed [batch:1] 946710010 0 0 ethernet x86_64
> Linux >= 0
> > >= 0 \
> > - 0 1 -1 - - - /opt/moab/tracefiles/testprogram - -1
> 0
> > [DEFAULT] \
> > 1 0 0 0 0 0 - - - - - - - 0.0 - - - - - -
> >
> > and my resource trace just has these:
> >
> > COMPUTENODE AVAILABLE 1 Node001 PBS 27580 6442
> 100000 2 -1 -1
> > -1 Linux \
> > x86_64 [NONE] [batch:1] [ethernet] 1.0 [NONE] [NONE]
> [NONE]
> > COMPUTENODE AVAILABLE 1 Node002 PBS 27580 6442
> 100000 2 -1 -1
> > -1 Linux \
> > x86_64 [NONE] [batch:1] [ethernet] 1.0 [NONE] [NONE]
> [NONE]
> >
> > and my moab.cfg:
> >
> > SCHEDCFG[Moab] SERVER=xxxxxxxxxxxxxxx:xx
> > MODE=SIMULATION
> > ADMINCFG[1] USERS=root,root
> >
> > SIMRESOURCETRACEFILE tracefiles/resource.trace
> > SIMWORKLOADTRACEFILE tracefiles/workload.trace
> > SIMSTOPITERATION 0
> > SIMSTARTTIME 00:00:00_01/01/00
> > SIMSTOPTIME 12:00:00_01/01/00
> >
> > RMCFG[base] TYPE=PBS
> >
> >
> > Are there any obvious mistakes I'm making?
> >
> > Thank you for any time you can spare to help someone new to
> Moab,
> > -Corby Ziesman
> > _______________________________________________
> > moabusers mailing list
> > moabusers at supercluster.org
> > http://www.supercluster.org/mailman/listinfo/moabusers
>
>
More information about the moabusers
mailing list